As name indicates, this time we are going to dig into NASA’s project management. We will assume you have already read the pervious blogs on this series, if not then go through them immediately as you people are missing something amazing.
Let starts with NASA’s project management of Mars Rover; this part will discuss NASA’s approach towards building Mars rover alongside with some flaws and managing errors. The project in whole is divided into multiple timelines which includes
Prelaunch: This is initial phase which includes pre-project planning, science definition and instrument selection, landing site selection, assembly and testing, and delivery of the spacecraft to Florida in preparation for launch. (Wilson, 2013)
Prelaunch: This is initial phase which includes pre-project planning, science definition and instrument selection, landing site selection, assembly and testing, and delivery of the spacecraft to Florida in preparation for launch. (Wilson, 2013)
Pre project planning constitutes of conceptual and requirement definition also including preliminary and technology development, these both are A and B phases respectively while selection of scientific instruments is also done in phase b. After that, in phase C, final design and fabrication of project is done followed by testing of instruments which is phase D.
Cruise: This timeline consists of duration of rover’s launch and its arrival at Mars, this timeline ends when mission is 45 days away from entering Martian surface

Approach: This includes the phase when mission reaches near red planet., engineers in this phase start intensive preparations for successful entry, descent, and landing of mission. This the time when engineers will shift to Mars time
Entry, Descent and Landing Phase: In this phase, rover enters into Mars atmosphere and management team will use high tech navigation technology to ensure safe descent of rover.

Surface Operations: This phase initializes when rover starts its operation phase i.e. investigating Mars surface day by day through its instruments. (Mission Timeline, n.d.)

Approach: This includes the phase when mission reaches near red planet., engineers in this phase start intensive preparations for successful entry, descent, and landing of mission. This the time when engineers will shift to Mars time
Entry, Descent and Landing Phase: In this phase, rover enters into Mars atmosphere and management team will use high tech navigation technology to ensure safe descent of rover.

Surface Operations: This phase initializes when rover starts its operation phase i.e. investigating Mars surface day by day through its instruments. (Mission Timeline, n.d.)
Coming back to project managerial point of view, this project is managed by NASA’s Science Mission Directorate and Jet Propulsion Laboratory (JPL) with an estimated cost of $2458.2 million. The project is designed to have mission timeline of two Earth year. As discussed above, NASA’s pattern towards mission completion is shown in fig:

During its phase B, this project affected by some setbacks while also during phase D, some components failed to operate. The initial setbacks were caused in sampling system (You didn’t get it ? I told u to go through pervious blogs), the setback was the delayed completion in this which may have resulted in delaying integration and testing part in May 2019, which in worst case scenario could have delayed project for 2 years. Another issue is with engineering drawing, these drawings are the mechanism by which engineers communicate to manufacturers the details of a component’s design. Other technical issues were with actuators, which are essential component for determining attitude and controlling mechanism of system, the issue was delay in supply of actuators, which would have led to delay in mission causing heavy loss. To overcome these technical issues, project management team have to alter some parts of project which include reducing time for complete development of other not so significant components and schedule duration was further reduced. The also developed less detailed integrated management system (IMS), integration of all organization's systems and processes in to one complete framework, enabling an organization to work as a single unit with unified objective, which benefited project’s ability to deal with challenges effectively. (NASA’S MARS 2020, 2017)
Concluding All, this mission entered in implementation phase in June 2016, and management team have showed confidence on launching mission in given time frame. There were some technical issues in beginning but were well answered by project management team although they have to cut off some of their components.
During its phase B, this project affected by some setbacks while also during phase D, some components failed to operate. The initial setbacks were caused in sampling system (You didn’t get it ? I told u to go through pervious blogs), the setback was the delayed completion in this which may have resulted in delaying integration and testing part in May 2019, which in worst case scenario could have delayed project for 2 years. Another issue is with engineering drawing, these drawings are the mechanism by which engineers communicate to manufacturers the details of a component’s design. Other technical issues were with actuators, which are essential component for determining attitude and controlling mechanism of system, the issue was delay in supply of actuators, which would have led to delay in mission causing heavy loss. To overcome these technical issues, project management team have to alter some parts of project which include reducing time for complete development of other not so significant components and schedule duration was further reduced. The also developed less detailed integrated management system (IMS), integration of all organization's systems and processes in to one complete framework, enabling an organization to work as a single unit with unified objective, which benefited project’s ability to deal with challenges effectively. (NASA’S MARS 2020, 2017)
Concluding All, this mission entered in implementation phase in June 2016, and management team have showed confidence on launching mission in given time frame. There were some technical issues in beginning but were well answered by project management team although they have to cut off some of their components.
Bibliography
Mission Timeline. (n.d.). Retrieved from Mars Exploration Rover:
https://marsmobile.jpl.nasa.gov/mer/mission/timeline/entry/launch/
(2017). NASA’S MARS 2020. Washington D.C.:
Office of Audits.
Wilson, M. (2013). Mars 2020 Mission Concept. DEIS
Scoping Public Meetings. Washington D.C.
Image Source: Retrieved from Mars Exploration Rover:
https://marsmobile.jpl.nasa.gov/mer/mission/timeline/entry/launch/

Comments
Post a Comment